January 25 2013 - As per OSHA - prior to demolition, all utilities should be marked out and the building/structure to be demolished should be isolated (water, sewer, gas, electric etc need to be disconnected)
OSHA states " One of the most important elements of the pre-job planning is the location of all utility services. All electric, gas, water, steam, sewer, and other services lines should be shut off, capped, or otherwise controlled, at or outside the building before demolition work is started. In each case, any utility company which is involved should be notified in advance, and its approval or services, if necessary, shall be obtained.
If it is necessary to maintain any power, water, or other utilities during demolition, such lines shall be temporarily relocated as necessary and/or protected. The location of all overhead power sources should also be determined, as they can prove especially hazardous during any machine demolition. All workers should be informed of the location of any existing or relocated utility service."